Every project step, weekly trash collection, lawn work, water and power update — with photos, costs and household sign-off.

Updates
4
Logged spend
TZS 132,500
Sign-offs
0
Trash collection

Weekly trash collection — week 33

10 Aug 2026

Bins emptied on schedule by the collection crew. Bin bay swept and washed afterwards, no overflow reported.

TZS 70,000

Weekly share of the TZS 280,000 monthly collection fee

0 approved0 comments

Registered households can sign off and comment. Register

Lawn & environment

Lawn mowing and hedge trimming

9 Aug 2026

Lawn worker mowed all common areas, edged the walkways along the old block and trimmed the fence-line hedge. Grass cuttings removed the same day.

TZS 62,500

Weekly share of lawn worker and fuel

0 approved0 comments

Registered households can sign off and comment. Register

Water

Water supply update

7 Aug 2026

Intermittent supply from the mains this week. Tanks were topped up and the community agreed to monitor pressure each morning until DAWASA confirms the line is stable.

0 approved0 comments

Registered households can sign off and comment. Register

Electricity

Electricity and compound lighting

6 Aug 2026

TANESCO outage on Sunday evening for about three hours. Entrance lighting is being reviewed alongside the proposed CCTV / security lights.

0 approved0 comments